S. Boise parking update

Chip sealing equipment in the IMSI parking lot
Chip-sealing equipment at IMSI

Parking lot closures will continue into the weekend at some facilities in the South Boise Correctional Complex.

On Friday, crews will chip seal the parking lot at Idaho Maximum Security Institution.

Also on Friday, they will seal half of the parking lots at Idaho State Correctional Institution and South Idaho Correctional Institution.

On Saturday, crews will finish the other halves of the parking lots at ISCI and SICI.

The following weekend, workers will return to clean and re-stripe all of the parking lots.

Idaho Department of Correction construction manager Mike McCabe says the contractor hopes to have all the work finished by the end of the month. 

The weather is the wild card. If we get more rain right before the chip sealing is scheduled to begin, the work will be postponed.